Standard Operating Procedure for Air Blower Sewage Treatment Plant

SOP Number: Hotel Engineering SOP  – 11

Department: Engineering and Maintenance

Date Issued: 22–Feb-2018

Time to Train: 20 Minutes

Air Blower For Sewage Treatment Plant Checklist and Procedure:

Required Tools:

  • Screwdriver.
  • Clamp meter.
  • Crimping Tool.
  • Megger.
  • Oil Can.
  • Air Blower.
  • Grease Gun.
  • Plier.
  • Spanner Set.
  • Brush.
  • Line Tester.

Consumable Parts:

  • PVC tape.
  • Old clothes.
  • WD- 40.
  • Lubricating Oil.
  • Grease.
  • Carbon removing compound.

Air Blower For Sewage Treatment Plant Maintenance Activity:

Motor:

  • Motor Should be of minimum 20 HP.
  • Electrical control should be proper.
  • Check for any burnt contact, loose electrical connection and overall operation to be checked.
  • Overload relay should be checked.
  • Check the operation of the relay, setting and loose electrical connections.
  • Check the timer operation and timer settings.
  • Check for any loose electrical connection.
  • Check for any burnt electrical connection.
  • Check the MCB rating and verify with the recommended Amp.
  • Check the motor bearing.
  • Perform oiling, greasing or change the bearing if required.
  • Check the internal Resistance Value.

Compressor:

  • The Compressor filter should be checked for any sand/dust and to be cleaned.
  • Air pressure setting in pressure gauge to be verified and set to the correct settings.
  • Check the V-belt if the same is loose or broken, then it should be replaced.
  • Check the bearing and do oiling/greasing.
  • The bearing to be changed if it is noisy.

Other points to check:

  • Check at the full Load motor capacity should be 28 Amp.
  • Check and verify the overload setting should be 16Amp.
  • Overload relay range should be between 14Amp to 23 Amp.
  • The timer Setting should be at 09 Sec.
  • Check and verify the control fuse rating at 4 Amp.
  • Check and verify the MCB rating should be at 100 Amp.

Remarks by the Technician:

Date:

Signature: